19_017 contract key items checklist

Developer’s contract key items checklist

1. Scope of work

  • Clearly define the scope of work, detailing the tasks, responsibilities, and deliverables expected from the property developer.

2. Start date of construction

  • Specify the agreed-upon start date for construction activities to commence.

3. Construction scheduling

  • Outline a comprehensive construction schedule, including milestones, phases, and anticipated timelines.

4. Construction completion date

  • Clearly state the expected date of project completion.

YouTube-Subscribe-LD

:rotating_light: You are missing out if you haven’t yet subscribed to our YouTube channel.

5. Rain days extension

  • Define provisions for extending project timelines due to inclement weather conditions.

6. Bonus and penalty fee clause

  • Outline any potential bonuses for early completion and penalties for delayed project delivery.

7. Cost saving split

  • Determine the percentage or method by which any cost savings achieved will be shared between the developer and the contractor.

8. Change orders

  • Specify the process for handling changes or additions to the original scope of work, including approval procedures and potential cost adjustments.

9. Guarantees

  • Clearly state any warranties or guarantees the developer provided regarding the work’s quality and durability.

10. Draw schedule

  • Define the Schedule for releasing payments to the developer based on project milestones or completion of specific tasks.

11. Reserve

  • Outline any provisions for setting aside funds as a reserve for unexpected project costs or contingencies.

12. Lien waivers

  • Include clauses related to obtaining lien waivers from subcontractors and suppliers upon payment to protect against potential liens on the property.

13. Backcharges

  • Detail procedures for addressing any costs incurred due to the developer’s negligence or errors.

14. Punch out

  • Define the process for addressing and rectifying any outstanding issues or incomplete work identified during a final inspection.

15. Warranty

  • Specify the duration and coverage of warranties provided by the developer for materials and workmanship.

16. Broom clean condition

  • Define the condition where the property should be left after the project, including cleanliness and debris removal.

17. Staging of phases

  • If applicable, outline the sequence in which different phases of the project should be completed.

18. Arbitration or litigation clause

  • Specify the method of dispute resolution, whether through arbitration or litigation, in case of conflicts between the parties.

19. Construction contract outline

  • Provide a high-level outline of the overall construction contract, indicating key sections and their corresponding page numbers.

Learn-More

Learn More

Here’s a simple breakdown of the key sections you’ll find in construction contracts, giving developers an idea of what’s covered:

Section 1: The contract documents

  • This section introduces all the papers that make up the contract and help guide the project.

Section 2: Work

  • Explains the tasks and things that need to be done in the project.

Section 3: Contractor’s duties and status

  • Talks about what the contractor is responsible for and their role.

Section 4: Time of starting and finishing

  • Covers when the work will begin and when it’s expected to be mostly done.

Section 5: Cost of the work and maximum cost

  • Deals with how much the project will cost and the most it should cost.

Section 6: Contractor’s payment

  • Discusses how much the contractor will get paid for doing the work.

Section 7: Changes in the work

  • Explains what happens if things need to change during the project.

Section 8: Costs to be paid back

  • Talks about which costs the developer will need to pay the contractor back for.

Section 9: Costs not to be paid back

  • Lists the costs that the developer won’t need to reimburse.

Section 10: Discounts, rebates, and refunds

  • If there are any deals or money coming back, this part explains it.

Section 11: Subcontracts and agreements

  • Deals with if the contractor hires others to help and other agreements they make.

Section 12: Accounting, cost control, and records

  • Explains how the money will be handled, how the costs will be controlled, and what records will be kept.

Section 13: Applications for payment

  • Talks about how the contractor asks to be paid.

Section 14: Paying the contractor

  • Explains how and when the contractor will get paid.

Section 15: Stored materials

  • If there are materials left over, this section says what can happen to them.

Section 16: Insurance

  • Talks about the insurance needed to keep the project safe.

Section 17: Notices

  • This part talks about how and when the people involved should communicate important information.

Section 18: Assignment, governing law, and subordination

  • Explains if and how the contract can be passed to someone else, the rules that apply to the contract, and how it relates to other agreements.

Section 19: Termination

  • Discusses when and how the contract can be ended before the project is finished.

Section 20: Indemnification

  • Explains who’s responsible if there are damages, losses, or costs because of the project.

Section 21: Miscellaneous provisions

  • Covers other important things that don’t fit in the earlier sections.